ACCELERATED CONSTRUCTION AND REHABILITATION OF BRIDGES
Author Info
BASU, BIKRAMADITYA
Permalink:
http://rave.ohiolink.edu/etdc/view?acc_num=ucin1116044680
Abstract Details
Year and Degree
2005, MS, University of Cincinnati, Engineering : Civil Engineering.
Abstract
The growing traffic demands and an aging transportation network necessitate highway construction to initiate and intensify efforts to accelerate repair and rehabilitation. Statistics show that vehicle miles have grown by 80 % between 1982 -2000 while the lane miles increased by only 3.8% during the same period. Any effort to close or restrict the highway for repair and rehabilitation work leads to unsafe conditions and major traffic delays. Extensive research has been conducted in various aspects of accelerated construction. Surveys have been conducted to identify factors for the success of different innovative contractual agreements. The contracts that were looked at for this work were design build, incentive/disincentive, A+B, warranty and Lane Rental. Research on accelerated construction has focused on the overall aspect of implementation of such concepts. This thesis however deals exclusively with the execution of the accelerated construction initiative by the Ohio Department of Transportation. Three bridges constructed under the initiative were chosen for study and research. The construction of the bridges, the ones in Guernsey, Clinton and Montgomery counties were observed by visiting the construction site, attending the pre and post construction meeting. These bridges used prefabricated post tensioned bridge decks. Data and information collected at the site and by interaction with different people associated in different capacity through the construction process was put together. The bridges in Clinton and Montgomery counties were compared because of the intrinsic similarity with the projects. Both were constructed using similar techniques and by the same contractor. One was a success and other not. The comparison revealed that small changes in the construction and planning were reflected in a substantial difference in project success. The conclusions and recommendations were based on the experience and understanding of the accelerated construction initiative. It showed that some of the areas that need to be worked on and improved upon for the project success are planning, changing of the existing mindset and other administrative issues and not technical aspects.
Committee
OSSAMA SALEM (Advisor)
Pages
94 p.
Subject Headings
Engineering, Civil
Keywords
Bridges
;
Construction
;
Accelerated bridge construction
;
Innovative bridge construction
;
ODOT's Strategic Innitiative
Recommended Citations
Refworks
EndNote
RIS
Mendeley
Citations
BASU, B. (2005).
ACCELERATED CONSTRUCTION AND REHABILITATION OF BRIDGES
[Master's thesis, University of Cincinnati]. OhioLINK Electronic Theses and Dissertations Center. http://rave.ohiolink.edu/etdc/view?acc_num=ucin1116044680
APA Style (7th edition)
BASU, BIKRAMADITYA.
ACCELERATED CONSTRUCTION AND REHABILITATION OF BRIDGES.
2005. University of Cincinnati, Master's thesis.
OhioLINK Electronic Theses and Dissertations Center
, http://rave.ohiolink.edu/etdc/view?acc_num=ucin1116044680.
MLA Style (8th edition)
BASU, BIKRAMADITYA. "ACCELERATED CONSTRUCTION AND REHABILITATION OF BRIDGES." Master's thesis, University of Cincinnati, 2005. http://rave.ohiolink.edu/etdc/view?acc_num=ucin1116044680
Chicago Manual of Style (17th edition)
Abstract Footer
Document number:
ucin1116044680
Download Count:
1,146
Copyright Info
© 2005, all rights reserved.
This open access ETD is published by University of Cincinnati and OhioLINK.